SCRUMstudy Certified Trainer (SCT) Sprint Practice Questions
The free SCRUMstudy Certified Trainer (SCT) questions that deal with sprint, with answers and explanations. The full bank and the timed practice test cover every topic the exam asks about.
Question #1
During a sprint planning meeting, the team estimates the user stories. What estimation technique could be used?
Correct answer: C
Explanation
Planning Poker allows team members to estimate story points collaboratively, ensuring everyone contributes.
Question #3
What is the primary purpose of a Sprint Review?
Correct answer: D
Explanation
The Sprint Review focuses on demonstrating the completed work to stakeholders and gathering feedback.
Question #4
In the middle of a sprint, a critical issue arises. What should the team do?
Correct answer: A
Explanation
Modifying the sprint goal allows the team to adapt to critical changes while staying focused on delivering value.
Question #8
A stakeholder requests a change during a sprint. What should the team do?
Correct answer: B
Explanation
Changes should be discussed at the next sprint planning to assess how they fit with the current sprint work.
Continue with SCRUMstudy Certified Trainer (SCT)
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in SCRUMstudy Certified Trainer (SCT), the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.