Question #2
Which contract type provides the contractor the most risk?
Correct answer: B
Explanation
Firm-Fixed Price contracts place the risk on the contractor since they must complete the work for the agreed-upon price.
Question #8
Under which circumstance can a contractor submit a claim?
Correct answer: B
Explanation
A contractor can submit a claim when their costs exceed the estimates agreed upon in the contract.
Continue with U.S. Department of Defense (DoD) Contract Specialist Exam
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in U.S. Department of Defense (DoD) Contract Specialist Exam, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.
All U.S. Department of Defense (DoD) Contract Specialist practice questions →