Question #2
A PMO is undergoing an evaluation to understand the impact of its maturity level on organizational benefits. The team is considering how increased maturity influences aspects such as cost, team size, and stakeholder value. What is typically true about a PMO with greater maturity?
Correct answer: D
Explanation
Higher maturity in a function means it is performed more sophisticatedly, raising the potential value delivered to stakeholders. Maturity does not require a bigger team or more functions.
Question #5
What essential aspects should be addressed in the development of action plans for the evolution of the PMO maturity?
Correct answer: A
Explanation
Maturity evolution action plans must address processes, people, and technology together, since a function's sophistication depends on all three dimensions.
Question #9
What does the target/desired maturity level for a function mean?
Correct answer: C
Explanation
Target maturity is the level of sophistication the PMO aims to reach for that function by the end of the evaluation cycle, and it should be equal to or above current maturity.
Continue with PMO-CP: PMO Certified Professional
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in PMO-CP: PMO Certified Professional, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.