Question #4
What is a key benefit of using a program management approach compared to managing projects individually?
Correct answer: B
Explanation
A program management approach emphasizes alignment across projects, leading to better resource utilization, conflict resolution, and achievement of strategic goals.
Question #5
During a program review, it is noted that one of the projects is behind schedule. What should the program manager do first?
Correct answer: A
Explanation
Investigating the cause of the delay will help the program manager understand the situation and determine the best course of action to address the issue.
Question #7
A new risk has been identified in the program affecting all projects. What action should the program manager take to address it?
Correct answer: B
Explanation
Developing a risk mitigation plan allows the program manager to proactively manage and address the newly identified risk before it escalates.
Continue with MSP Practitioner — MSPP
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in MSP Practitioner — MSPP, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.