CSM-001 Sprint Practice Questions
The free CSM-001: Certified Scrum Master questions that deal with sprint, with answers and explanations. The full bank and the timed practice test cover every topic the exam asks about.
Question #7
Which of the following activities do not occur at the end of the Sprint?
Select 2 answers.
Correct answer: A, D
Explanation
Development and testing happen throughout the Sprint so the increment is already Done when it ends; what closes the Sprint is the Sprint Review and Retrospective, with deployment of the completed increment.
Question #8
A _____ is created during the first half of the Sprint planning meeting and a _____ is created during the second half of the Sprint planning meeting?
Correct answer: A
Explanation
In the first half the team selects backlog items and forms the Sprint Backlog with the Product Owner; in the second half it decomposes those items into the collection of tasks needed to build them.
Continue with CSM-001: Certified Scrum Master
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in CSM-001: Certified Scrum Master, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.