Question #1
A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?
Correct answer: D
Explanation
Releasing team members and archiving project documents are closing activities, performed after the deliverables are accepted and transitioned.
Question #3
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
Correct answer: B
Explanation
The MOA records the agreed terms between the company and the outsourced team, including the working-hour limits the project manager overlooked when fast tracking.
Continue with PK0-004: CompTIA Project
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in PK0-004: CompTIA Project, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.